  • Start date: March 2, 2017
  • Completion date: March 8, 2017
  • Work: Erosion control of slopes at the Balao-Esmeraldas road, using GMAT-R560
  • Contractor: GEINCO
  • Extension: 5.000,00 m2
  • Product:  GMAT-R560
  • Conclusions:
  • The construction project of the Balao-Esmeraldas road has specified the protection of the slopes against wind and water erosion. The total protected area is approximately 5,000.00 m2.
  • GMAT R560 installation, subjected to several tests with Gripple anchors.
  • Slopes are formed by the cut of the wall and by eviction of material product of the excavation for the platform of an educational unit.